The progress update for the various components of the Southern Integrated Gateway until 30th April 2008 are as follows :-
| COMPONENT |
SCHEDULE ( % ) |
ACTUAL ( % ) |
Section 1
(CIQ Building) |
100 |
100 |
Section 2
(JB Central Building) |
100 |
92 |
Section 3
(Western Hub JBS) |
54 |
34 |
Section 4
(Short Term Access) |
100 |
92 |
Section 5
(Custom Marine Complex Tg. Surat) |
100 |
100
|
Section 6
(Trackworks, Signal & Telecommunication) |
76 |
53 |
Section 7
Trackworks, Signal & Telecommunication Line 1 |
0 |
0 |
| Medium Term Link ( formerly Permanent Link ) |
0 |
5 |