GSB PROJECT COMPONENTS: WORK PROGRESS
( as at Jan 2005 )
Customs, Immigration and Quarantine (CIQ Complex ):
All earthworks and piling works for CIQ Complex have been
completed.Precast column,
beam and slab construction are proceeding and reinforced
concrete work for lift cores
and retaining walls are in progress. A few mock-up works
for Finishes, Mechanical & ICT
have been carried out
CIQ Complexs Jan 2005
RE works for CIQ
CIQ Complexs from Interchange 1
Progress of Roof erection for LV South
Main Substation construction Jan 05
Progress of curtain wall works
Substation No. 1 construction Jan 05
JOHOR BAHRU SENTRAL ( JBS ) :
Earthworks, bored pile installation, construction of Reinforced
Earth walls and construction
of ground beams are in progress.
JB Sentral
- Construction of piles, reinforced earth and ground
beams - Jan 2005
Construction of ground beam
Interchange No. 1:
Piling works for interchange 1 have been completed.Earthworks,
Underpass 1, Underpass 5 , Bridge No. 1 and drainage works
are in progress.
Deck
slab works for Underpass 1
Excavation
works & concreting for Underpass 5
Interchange 1 - Jan
05
Construction
of Underpass 2 & 3
Works on Bridge 1
Box
girder works at bridge No.1
Infrastructure works:
Infrastructure works i.e main drain and demolition of existing
Tanjung Puteri bridge are in progress.