GSB PROJECT COMPONENTS: WORK PROGRESS
( as at October 2005 )
Costoms, Immigration and Quarantine ( CIQ Complex )
All earthworks and piling works for CIQ Complex have been
completed.Precast column, beam and slab construction are
proceeding and reinforced concrete work for lift cores and
retaining walls are in progress. A few mock-up works for
Finishes, Mechanical & ICT have been carried out
CIQ Complexs Oct 2005
Progress at HGV North
Progress at HGV South
Progress of Roof erection for LV South
JOHOR BAHRU SENTRAL ( JBS ) :
Earthworks, bored pile installation, construction of Reinforced
Earth walls and construction of ground beams are in progress
JB Sentral
- Construction of piles, reinforced
earth and ground beams - Oct 2005
Construction of column &
slab
Interchange No. 1:
Piling works for interchange 1 have been completed.Earthworks,
Underpass 1, Underpass 5 , Bridge No. 1 and drainage works
are in progress
Box girder works at bridge No.1
Interchange
1 - Oct 05
Box girder
works at Bridge No. 2
Infrastructure works:
Infrastructure works i.e main drain , relocation works for
PUB pipes and piling for Tanjung Puteri Bridge are in progress.