GSB PROJECT COMPONENTS: WORK PROGRESS
( as at April 2004 )
Customs, Immigration and Quarantine (CIQ Complex ):
All earthworks and piling works for CIQ Complex have been
completed.Precast column, beam and slab construction are
proceeding and reinforced concrete work for lift cores
and retaining walls are in progress.
CIQ Complex
- April 2004
Substation 1 construction
Brickwork at CIQ
Main Substation construction Apr 04
Crib wall construction at main substation
JOHOR BAHRU SENTRAL ( JBS ) :
Earthworks, bored pile installation, construction of Reinforced
Earth walls and laying of main drains are in progress.
JB Sentral - Construction of piles, reinforced
earth and main drain - Apr 2004
JB sentral - construction of RE walls
- Apr 2004
Piling works for sky bridge between JBS & CIQ
Interchange No. 1:
Piling works for interchange 1 have been completed.Earthworks
and drainage works are in progress.